Back to Case Studies Building Group logo Building Group
Case Study · Flat Roof

Worsley EPDM Flat Roof Replacement

Failing mineral felt flat roof on a single-storey rear kitchen extension stripped back to deck and rebuilt with corrected falls, single-piece Firestone EPDM rubber membrane, hand-formed Code 4 lead apron, and GRP edge trim. Five working days, fixed price £4,850, zero seams, twenty-year manufacturer warranty.

Worsley, Salford 5 working days £4,850 fixed price 20-year warranty
38 m² Flat Roof Area
5 days Working Programme
£4,850 Fixed Price
0 Seams in Membrane
20 yr Manufacturer Warranty

Project Overview

A homeowner in Worsley had a problem most families with an early-2000s rear extension recognise. The original three-layer mineral felt flat roof above the kitchen was eighteen years old, and what had started as occasional damp patches on the kitchen ceiling had escalated, over the previous two winters, to a slow but reliable drip.

Two earlier patch repairs by separate contractors had each lasted around eight months. By the time we were called the felt was visibly blistered across most of the roof, ponding had formed permanent dark stains where standing water had sat for weeks at a time, and the homeowner had stopped trusting any patch quote on principle.

We recommended a full strip-and-replace down to the deck level — not a fourth patch, and not an overlay. The deck itself turned out to need replacing too, which was scoped from day one rather than priced as a discovery. Five working days later the family had a single-piece EPDM rubber roof with corrected falls, manufacturer-warranted for twenty years.

The Client Brief

The brief was short and clear: solve it permanently, do not overlay the old, and make sure the next person who looks at this roof in twenty years' time has nothing to fix.

The contracted ceiling was £4,850 inclusive of VAT, tower scaffolding, materials, labour, waste removal and certification. No contingency was held; everything that could go wrong on a flat roof of this size had already been priced in.

The Challenge

Six things made this flat roof job more demanding than a routine felt swap.

Failed Mineral Felt

The original three-layer torch-on felt had reached the late stage of UV degradation. The top layer was blistered across roughly 60% of the area, and at least four pinhole leaks had been confirmed via internal staining. There was no patch repair scenario that would have outlived another full winter.

Decking Condition

Original 18mm chipboard deck. Once felt fails on a chipboard deck, water ingress damages the deck rapidly. We scoped 100% deck replacement to OSB3 from day one rather than gamble on partial salvage. On strip, the chipboard was confirmed compromised across most of the area — the right call.

Inadequate Falls & Ponding

The original roof was constructed with falls of approximately 1:80, well below the 1:40 minimum recommended by current best practice for flat roofs. Ponding water had stained the felt and accelerated its failure. The rebuild was an opportunity to install proper 1:40 falls using furring strips on the new deck.

House Wall Abutment

The flat roof abuts the rendered rear wall of the two-storey main house along its full back edge. The detail at this junction is the single most common failure point on a flat roof. Hand-formed Code 4 lead apron flashing, dressed up the EPDM upstand and chased into the render with mortar, was specified rather than relying on a sealant-only approach.

Two Penetrations

One roof lantern (kitchen island skylight) and one soil vent pipe. Both required pre-formed Firestone EPDM corner pieces and bonded sleeves rather than site-cut details. The penetration details account for a disproportionate share of failed flat roofs in the trade and are worth slowing down for.

5-Day Weather Window

EPDM bonding adhesive requires dry surfaces and air temperature above 5°C. The job was booked into a high-pressure mid-spring slot with two contingency days held in reserve. Tarp-and-go was non-negotiable. The deck phase carries the highest weather risk — we stripped, decked, vapour-barriered and primed within the same shift to prevent any overnight exposure of bare deck.

Our Approach

Flat roofs fail at details, never in the field. Our approach put detail discipline ahead of speed.

Survey from above and from below. We accessed the roof for visible-defect mapping and we also examined the kitchen ceiling internally with a moisture meter. The combination of external blistering and internal damp staining gave us a clear picture of where the active leaks were and let us write a written scope rather than a visual estimate.

EPDM not felt, deliberately. Mineral felt is the cheapest spec on the day. EPDM is roughly 30% more expensive at install but carries a 20-year manufacturer warranty against felt's typical 10. Across a normal household ownership window the EPDM is the cheaper roof. We explain the maths once, the client makes the call once, and nobody returns for a re-roof in eight years.

Single-piece membrane, zero field seams. EPDM can be installed in panels with bonded seams or as a single field-cut piece. Field-cut single-piece is the best long-term outcome — no seams to age, no overlap to fail. We measured the deck, ordered a 7m x 6m sheet (with 600mm overhang each side), and bonded it as one piece.

Falls corrected on rebuild, not preserved. A common shortcut is to rebuild the roof on the existing falls because the deck and joists are still in place. We installed graduated furring strips on the new deck to bring the fall up from approximately 1:80 to the recommended 1:40. Two extra hours of work. Eliminates ponding for the lifetime of the roof.

Lead apron, not sealant. The abutment to the main house wall is hand-formed Code 4 milled lead, dressed up over the EPDM 150mm upstand and chased into the render with a 25mm chase and pointed in lime-rich mortar. Sealant-only details on this junction fail in five to seven years; lead apron details outlast the membrane.

Manufacturer warranty registered, not just promised. Firestone EPDM warranties are valid only when installed by an approved installer and registered with the manufacturer in the homeowner's name. We do this within seven days of completion and email the certificate to the homeowner directly. The warranty is theirs, not ours.

The Build Process

Five working days from scaffolding-up to handover. Six discrete stages, each photographed and signed off before the next began.

01
Day 1, AM

Tower Scaffold & Felt Strip

Tower scaffold erected to the rear elevation with edge protection and a debris chute. Skip positioned on the driveway with permit. Existing mineral felt stripped in panels to a tarpaulin staging area, photographed for the project file, and dropped to the skip via the chute. Three of the four suspected leak points confirmed visually on strip.

02
Day 1, PM

Deck Strip & Joist Inspection

Original 18mm chipboard deck lifted in sections. Underlying timber joists inspected for rot, splitting and fixing fatigue. All joists found sound — no remediation required. Joist tops cleaned, residual fixings extracted, debris removed. Roof tarped and tied off for the overnight period.

03
Day 2

New OSB3 Deck with Corrected Falls

Graduated tapered furring strips installed across the joists to bring falls from the original 1:80 up to a uniform 1:40 toward the new outlet position. New 18mm OSB3 tongue-and-groove deck installed and screw-fixed at 200mm centres to the joists. Sarnavap 1000E self-adhesive vapour barrier laid across the deck and sealed at all penetrations. Fully weathertight at end of shift.

04
Day 3

Insulation & Edge Trim

100mm Recticel Powerdeck flat-roof PIR insulation board laid over the vapour barrier in a staggered-joint pattern. 150mm timber upstand fitted to the house-wall abutment line. GRP two-piece kerb and drip trim system mechanically fixed to the front and side perimeters. New 75mm aluminium scupper outlet installed through the fascia and connected to the existing rainwater downpipe.

05
Day 4

EPDM Single-Piece Membrane

Firestone RubberCover EPDM single-piece membrane (7m x 6m, 1.2mm thickness) brought to roof, unrolled, allowed to relax for the manufacturer-specified period, then bonded to the insulation board with Firestone Bonding Adhesive across the field area. Perimeter detail bonded with Firestone Water Block sealant. Membrane dressed up the 150mm upstand at the abutment.

06
Day 5

Penetrations, Lead Apron, Inspection & Sign-Off

Roof lantern and soil vent pipe penetrations detailed using pre-formed Firestone EPDM corners and bonded sleeves per manufacturer's spec. Hand-formed Code 4 lead apron flashing dressed over the membrane upstand and chased 25mm into the render, pointed in lime-rich mortar. Final inspection by project lead with photographic documentation. Tower scaffold struck. Site cleaned. Manufacturer warranty registered to the homeowner within the same day.

Project Specifications

Manufacturer-warranted spec, with the supporting numbers.

EPDM Membrane

Firestone RubberCover EPDM single-piece membrane, 1.2mm thickness, custom-cut to 7m x 6m to suit deck dimensions plus 600mm overhang. Zero field seams. 20-year manufacturer warranty.

Decking

18mm OSB3 tongue-and-groove flat roof decking, screw-fixed at 200mm centres to existing timber joists. 100% replacement of original failed chipboard.

Falls

Graduated tapered furring strips installed across joists to deliver uniform 1:40 fall toward outlet. Corrected from original measured 1:80 fall to current best-practice minimum.

Vapour Barrier

Sarnavap 1000E self-adhesive vapour control layer laid across the deck before insulation, with sealed laps at all penetrations. Protects the deck from interstitial condensation.

Insulation

100mm Recticel Powerdeck flat-roof PIR insulation board, staggered-joint laid over the vapour barrier. Achieves a U-value of approximately 0.18 W/m²K through the build-up.

Lead Apron

Code 4 milled lead apron flashing to BS EN 12588, hand-formed on site, dressed up the EPDM 150mm upstand and chased 25mm into the render of the abutting house wall, pointed in lime-rich mortar.

GRP Edge Trim

GRP two-piece kerb and drip trim system installed at front and side perimeters. UV-stable, mechanically fixed, no painting or maintenance over the life of the membrane.

Penetration Details

Pre-formed Firestone EPDM corner pieces and bonded sleeves at the roof lantern and soil vent pipe. Manufacturer-spec details rather than site-cut, eliminating the most common flat-roof failure mode.

Outlet

75mm aluminium scupper outlet through the fascia, sized to current Building Regs minimum, connected to the existing rainwater downpipe with new connection fittings.

Performance vs Targets

Field seams in membrane
target zero (single-piece install)
0 seams
Falls
target 1:40 minimum
1:40 throughout
Decking replacement
scoped 100% from day one
100% replaced
Programme
contracted 5 working days
delivered day 5
Tarp-and-go discipline
weathertight every shift end
100% across 5 days
Penetration details
manufacturer pre-formed parts
2 of 2 detailed to spec
Final account
contract sum £4,850
£4,850 settled
Manufacturer warranty
registered within 7 days
registered same day
Snagging items at handover
target zero
0 raised

The Finished Result

What was delivered

A 38 m² flat roof over the rear kitchen extension, fully replaced from joist-tops upwards: new OSB3 deck with corrected 1:40 falls, vapour barrier, PIR insulation, GRP edge trim, single-piece Firestone EPDM membrane bonded as one continuous sheet with zero field seams, hand-formed Code 4 lead apron at the house-wall abutment, and pre-formed manufacturer-spec details at both penetrations.

Five working days, fixed-price £4,850 settled at the contracted figure with no variations and no snagging. The Firestone manufacturer warranty was registered to the homeowner the same day as completion. One winter has now passed without a single drip into the kitchen below.

0 Field Seams
1:40 Corrected Falls
20 yr Manufacturer Warranty
30 yr Workmanship Guarantee

What the Client Said

We had been promised a permanent fix twice already by other firms, both of which failed inside a year. Building Group were the first people who told us straight that a fourth patch would be a waste of our money and that what we needed was a proper strip-and-replace down to the deck. They priced it once, didn't change the price, finished it on the day they said they would, and registered the manufacturer warranty in our name straight away. The roof has been through one full winter and three big storms without a drop coming through. Worth every penny.

Mr S. Holroyd Worsley, Salford · April 2026

More Roofing Case Studies

Flat Roof Failing?

If your flat roof is leaking, blistered, ponding or coming up to twenty years old, we'll come out for a free flat roof survey, photograph what's actually going on, and put a fixed-price replacement contract on the table. No overlay shortcuts, no surprises, single-piece EPDM with twenty years of manufacturer-warranted peace of mind.

Get Your Free Flat Roof Survey