Case Study · Specialty Coffee Fit-Out

Knutsford Coffee Shop

A 110m² specialty coffee shop fit-out for an independent owner-operator in a heritage high-street demised unit in Knutsford, Cheshire — 18-cover front-of-house with bench seating along the south wall and a window-bar position, La Marzocco Linea PB 2-group espresso bar with Mahlkönig grinders and dedicated BWT bestmax water filtration, full commercial kitchen for breakfast and lunch service with DW172-compliant grease extraction routed to roof level via the existing service riser, an in-situ poured terrazzo floor, a bespoke American oak timber-clad serving counter as the joinery centrepiece, and a refreshed shopfront respecting the conservation area context. Seven-week programme delivered against fixed price; Cheshire East EHO pre-opening sign-off received ahead of the contracted soft-launch Saturday.

Knutsford, Cheshire 7 weeks £88,000 fixed price 110 m² / 18 covers
110 m²Demised Unit
7 wksBuild Duration
£88kFixed Price
18Front-of-House Covers
Sat AMSoft Launch on Date

Project Overview

An independent specialty coffee owner-operator — a former barista with several years behind the bar at a well-regarded Manchester roastery and Q-grader certification — took on a 110m² high-street demised unit on the main run through Knutsford, Cheshire, on a 10-year lease. The unit had previously traded as a small clothing retailer and was being repurposed as a specialty coffee shop with full breakfast and lunch service. The brief was simple in intent and demanding in detail: an 18-cover front-of-house centred on a bespoke American oak timber-clad serving counter with a La Marzocco Linea PB 2-group espresso bar, a back-of-house full commercial kitchen for breakfast and lunch service with DW172-compliant grease extraction routed to the rear roof level, an in-situ poured terrazzo floor as the visual anchor, and a refreshed shopfront respecting the existing conservation area context.

We were one of three contractors invited to quote. Our price came in second by approximately £4,500 against the leading offer. We won the work because our quotation was the only one to (a) include the DW172-compliant grease extraction duct design and the structural-route survey through the existing service riser inside the contract sum rather than as a "subject to landlord agreement" provisional, (b) coordinate the La Marzocco Linea PB and Mahlkönig grinder install with the dealer at procurement stage so that the services to the counter were positioned correctly when the joiner pre-routed them off-site, and (c) treat the in-situ poured terrazzo as a defined 5-day workstream (mix, pour, cure, grind, polish, seal) with the specified aggregate mix ordered in week one against a 4-week supplier lead time rather than left as a finishing-trade catch-up activity.

Practical completion was certified on the contracted Friday. Cheshire East Council Environmental Health Officer attended the pre-opening visit Friday afternoon and signed off the food safety management system, the grease extraction certification, the hand-wash basin separation and the integrated pest-control sealing in a single visit with no remedial actions logged. The owner-operator opened to the public for a soft launch the following Saturday morning. The first espresso pulled at 7.30am went to the next-door bookshop owner who had walked across to say good luck. The first paying customer arrived at 7.34am.

The Client Brief

The brief came from the owner-operator directly across two long site walks before contract signature. Priorities, in their stated order:

The Challenge

A 7-week specialty coffee shop fit-out for an independent owner-operator in a conservation-area high-street demised unit is a different discipline from a corporate Cat-B fit-out or a developer-led new-build. The grease extraction route through the existing service riser is the single hardest design problem; the La Marzocco install lives or dies on three millimetres of service positioning under the counter; the in-situ terrazzo is a 5-day continuous workstream that doesn't compress; and the EHO pre-opening visit is the gating event before the owner can sell a single coffee.

DW172 Grease Extraction Through the Service Riser

The kitchen extract canopy over the cooking line had to vent to roof level to comply with DW172 (the HVCA Standard for Kitchen Extract Ventilation) and to avoid odour or grease nuisance to the residential flat above. The route through the existing rear service riser was tight: 350mm internal diameter required, riser available diameter 410mm, with a fire-rated boxing at the second-floor structural penetration. We surveyed the riser at quotation stage with the landlord's facilities manager on a joint walkdown, agreed the route in writing, and priced the duct, the silencers, the roof-level fan, the fire-rated boxing and the gas-isolation interlock as a fixed sub-contract within the contract sum. Commissioned and certified at week 7.

La Marzocco Install Coordination

A La Marzocco Linea PB 2-group on a 32A single-phase circuit with 15mm mains water and 22mm waste needs the services positioned to the millimetre under the counter for the dealer's installer to land the machine cleanly. We engaged the La Marzocco UK dealer (Coffee Service Group) at procurement stage in week one: confirmed the machine model, the grinder pairing (Mahlkönig E80 Supreme and EK Omnia), the BWT bestmax M water filtration housing position, the drip-tray waste route, and the under-counter clearances. Services pre-routed to floor positions before the bespoke counter joinery arrived from the workshop, counter installed week 6, dealer installed and commissioned the espresso bar week 7.

Bespoke American Oak Timber-Clad Counter

The serving counter is the visual centrepiece of the shop and a piece of joinery that earns its place on the photographs. Vertically-oriented 25mm American oak slats on a marine-ply substrate, finished in a natural matt-oil; 40mm honed quartz worktop in a warm-grey selected to suit the terrazzo aggregate palette; a hand-formed copper drip tray let into the worktop in front of the espresso machine. Off-site fabricated by a specialist heritage joiner over weeks 3-5 on the same fixed-price-sub-contract methodology we used for the heritage joinery on the Birmingham Colmore Row HQ Fit-Out earlier in the year. Delivered week 6, installed Tuesday-Wednesday with the joiner on site for the install.

In-Situ Poured Terrazzo (5-Day Workstream)

In-situ poured terrazzo is the floor specialty-coffee owner-operators are willing to spend on. The specified aggregate mix — warm-tone brass, white, and grey on a pale matrix — carried a 4-week supplier lead time placed at week one. The pour-grind-polish-seal workstream is 5 continuous days that don't compress: mix and pour Monday, initial cure Tuesday, first grind Wednesday, second grind and polish Thursday, polish and seal Friday. Placed on the master programme in week 5, so the floor was ready to take the bespoke counter, the seating and the kitchen equipment in week 6 without any back-tracking.

Cheshire East EHO Pre-Opening Sign-Off

The Environmental Health pre-opening visit is the gating event before the owner-operator can serve a single customer. We engaged Cheshire East Environmental Health pre-bid with our DW172 grease extraction calculations and the food-flow layout drawing, and we wrote the sign-off as a contractual milestone for the Friday afternoon of week 7. EHO attended on the contracted Friday, signed off the food safety management system (HACCP), the grease extraction certification, the hand-wash basin separation from prep sinks, the food-grade flooring cove-skirting under the prep area, the hot-water provision at every basin, and the integrated pest-control sealing in a single visit. Zero remedial actions logged.

Conservation Area Shopfront

Knutsford's central run is within a designated conservation area; the existing timber fascia and pilasters carried local-character significance and could not be replaced. We retained the existing timber framing, repaired and repainted in a heritage-tone dark green agreed in writing with Cheshire East planning at quotation stage, and obtained signage consent for the brand's hand-painted gilded fascia lettering pre-bid so that the signwriter could be booked and delivered without becoming a programme item. Signwriter on site week 6 for the fascia; finished signage in place by Friday of week 6 ahead of the soft launch.

Our Approach

Independent specialty coffee fit-outs succeed or fail on the technical disciplines that don't show up in the photograph: the grease extraction, the espresso bar service positioning, the EHO sign-off, the conservation-area shopfront permissions. Our approach was built around four governance disciplines and one programme discipline.

Grease extraction owned end-to-end as a contractual workstream. The two competing quotes treated the grease extract as "subject to landlord and EHO agreement, provisional sum to apply". We surveyed the existing service riser pre-bid with the landlord's facilities manager, calculated the duct sizing and the roof-level fan capacity, and priced the full DW172-compliant package as a fixed sub-contract within the contract sum. Commissioned and certified at week 7; gas-isolation interlock with canopy fire-suppression tested live with the EHO on the Friday afternoon visit.

La Marzocco dealer engaged at procurement stage. The two competing quotes treated the espresso bar install as a "tenant-supply" item to be addressed at handover. We engaged the La Marzocco UK dealer (Coffee Service Group) in week one to confirm the machine and grinder pairing, the under-counter service positions and the dealer's installer mobilisation date. Services pre-routed to floor positions before the bespoke counter arrived from the workshop. Dealer's installer landed the espresso bar cleanly in week 7 with no service-position remedial.

Terrazzo as a 5-day workstream, not a finishing trade. The two competing quotes treated the terrazzo as a "month-7 finishing item" with the aggregate mix specified at the time. In-situ terrazzo aggregate mixes carry 4-week supplier lead times; left to month seven, that means a slipped programme. We placed the aggregate order in week one against a 4-week lead time, sequenced the pour-grind-polish-seal workstream as 5 continuous days in week 5, and protected the floor through the joinery and kitchen equipment install in weeks 6-7 with full sheet protection.

EHO pre-opening engaged pre-bid. Environmental Health visits are the gating event for any new hospitality opening. The two competing quotes treated the EHO visit as a "client to arrange" item. We engaged Cheshire East Environmental Health pre-bid with our DW172 calculations and the food-flow layout drawing, agreed the inspection criteria and booked the Friday afternoon of week 7 as a contractual milestone. Sign-off received in a single visit with zero remedial actions; soft launch Saturday morning unblocked.

Programme float held as fixed. 5 days of weather-and-trade-clash contingency held as fixed float on the master programme; one shift lost across the 7 weeks (a delivery slot rescheduled by the landlord), absorbed without consuming critical-path float. PC certified on the contracted Friday afternoon. EHO sign-off on the Friday afternoon. Soft launch Saturday morning at 7.30am.

The Build Process

Thirty-five working days from key handover to the first espresso pull. A landlord-and-EHO-led mobilisation, four long-lead specialist orders placed in week one, an in-situ terrazzo workstream sequenced as a continuous 5 days, and a soft-launch Saturday morning held to the time.

01
Week 1

Mobilisation, Strip-Out & Long-Lead Orders

Possession of the demised unit Monday morning. Strip-out of the previous clothing-retail fit-out: existing partitioning, fitted display joinery, dated carpet, dropped suspended ceiling on the rear half of the unit. Pre-strip asbestos R&D survey by an independent UKAS-accredited surveyor confirmed no asbestos-containing materials in the prior fit-out (post-1999). Joint walkdown of the rear service riser with the landlord's facilities manager confirmed the grease duct route. Long-lead specialist orders placed: terrazzo aggregate mix (4-week lead), bespoke American oak counter joinery (4-week off-site fabrication), kitchen extract canopy and roof-level fan (3-week lead), La Marzocco Linea PB and Mahlkönig grinders (dealer-supply, 5-week lead).

02
Week 2

Partitions, Kitchen Wall Build & First-Fix M&E

Metal stud partitioning to define the front-of-house, the back-of-house kitchen and the small staff WC. Wall build to the kitchen with a 60-minute fire-rated leaf to the residential flat above. First-fix electrical: dedicated 32A single-phase circuit to the espresso bar position, dedicated 16A circuits to each grinder, dedicated 32A 3-phase circuit to the commercial dishwasher, dedicated lighting circuits zoned for the 5-scene controller, low-level lighting circuits behind the back bar. First-fix plumbing: 15mm mains water with isolation valve to espresso bar position, 22mm waste to under-counter gully, hot and cold to all kitchen positions and hand-wash basins (separate from prep sinks).

03
Week 3

Grease Extract Duct Install & Joinery Off-Site

Kitchen extract canopy installed over the cooking line, dedicated grease arrestors and replaceable grease filters fitted. Stainless-steel ducting routed to roof level via the existing service riser: 350mm internal diameter, fire-rated boxing at the second-floor structural penetration, inline silencers to control fan noise. Roof-level fan landed on the existing roof plant area. Bespoke American oak counter joinery in off-site fabrication; first-fix services pre-routed to the floor positions agreed with the joiner against the dealer's espresso-bar service-positioning drawing.

04
Week 4

Plasterboard, Decoration Prep & Floor Substrate Levelling

Plasterboard taped, jointed, sanded and prepared for paint across all walls and the new ceilings. Floor substrate levelled and screeded to the tolerance required for the in-situ terrazzo pour the following week (FF/FL flatness verified). Conservation-area shopfront paint preparation: existing timber fascia and pilasters sanded back, primed in heritage-tone undercoat ready for the dark-green topcoat. EHO pre-opening visit booked in writing with Cheshire East Environmental Health for the Friday afternoon of week 7.

05
Week 5

Terrazzo 5-Day Pour-Grind-Polish-Seal

The critical week. Monday: in-situ terrazzo mixed on site with the specified aggregate mix (warm-tone brass, white, grey on a pale matrix), poured across the front-of-house and customer-side circulation, hand-trowelled to a level finish. Tuesday: initial cure under polythene protection. Wednesday: first grind by specialist terrazzo contractor exposing the aggregate. Thursday: second grind to a 600-grit honed finish. Friday: polish and seal with food-area-rated penetrating sealer. Floor protected from Friday evening through to week 7 with full sheet protection.

06
Week 6

Counter Install, Decoration & Conservation Shopfront

Bespoke American oak counter delivered Monday, installed by the joiner on site Tuesday-Wednesday: vertically-oriented 25mm oak slats on the customer-facing leaf, 40mm honed quartz worktop bedded down, hand-formed copper drip tray let into the worktop. Glass display section on the customer side fitted. Decoration: two coats of paint to all walls and ceilings in the heritage-tone palette selected by the owner-operator. Conservation-area shopfront topcoat applied in heritage-tone dark green. Specialist signwriter on site Thursday for hand-painted gilded fascia lettering; finished signage in place Friday of week 6.

07
Week 7

Kitchen Equipment, La Marzocco Install, EHO & Soft Launch

Kitchen equipment landed Monday: Lincat double oven, induction hob, salamander, Italian grill, bain-marie, twin-basket fryer, twin-deck commercial dishwasher, under-counter prep refrigeration. Gas Safe-registered commercial engineer commissioned the gas worktop equipment Tuesday. La Marzocco UK dealer (Coffee Service Group) on site Wednesday for the Linea PB and Mahlkönig grinder install: services landed cleanly to pre-routed positions, BWT bestmax M water filtration commissioned, espresso machine pulled its first calibration shot Wednesday afternoon. Front-of-house furniture (loose tables, bench seat upholstery, window-bar stools) installed Thursday. Snag round Thursday afternoon: 19 items closed by Friday lunchtime. Cheshire East EHO pre-opening visit Friday afternoon: HACCP signed off, grease extraction certified, hand-wash separation verified, food-grade flooring inspected, hot-water provision verified. Zero remedial actions logged. PC certificate issued Friday afternoon. Soft launch Saturday morning, first espresso pulled at 7.30am.

Project Specifications

The technical detail behind a 110m² specialty coffee shop fit-out built to DW172 grease extraction compliance, a La Marzocco install coordinated at procurement stage, and a 5-day in-situ terrazzo workstream sequenced against an EHO pre-opening visit and a soft-launch Saturday.

DW172 Grease Extraction

Stainless-steel kitchen extract canopy over the cooking line with dedicated grease arrestors and replaceable grease filters. 350mm-diameter ducting to roof-level fan via existing service riser, fire-rated boxing at structural penetration, inline silencers for noise control. Gas-isolation interlock with canopy fire-suppression tested at commissioning. DW172 compliance certificate issued at PC.

La Marzocco Espresso Bar

La Marzocco Linea PB 2-group espresso machine on 32A single-phase circuit, 15mm mains water with BWT bestmax M dedicated water filtration, 22mm waste to under-counter gully. Mahlkönig E80 Supreme espresso grinder and Mahlkönig EK Omnia batch-brew grinder on 16A circuits each. Dealer-supplied install coordinated at procurement; commissioned week 7.

Bespoke Counter Joinery

Bespoke serving counter in vertically-oriented 25mm American oak slats on a marine-ply substrate, finished in a natural matt-oil. 40mm honed quartz worktop in warm grey. Hand-formed copper drip tray let into the worktop in front of the espresso machine. Off-site fabricated by specialist heritage joiner over 4 weeks; installed week 6.

In-Situ Poured Terrazzo

In-situ poured terrazzo across front-of-house and customer-side circulation in a specified aggregate mix (warm-tone brass, white, grey on pale matrix). 5-day pour-grind-polish-seal workstream in week 5: pour Monday, cure Tuesday, first grind Wednesday, second grind Thursday, polish-and-seal Friday. Food-area-rated penetrating sealer. 600-grit honed finish.

Commercial Kitchen Equipment

Cooking line: Lincat double oven, induction hob, salamander, Italian grill, bain-marie, twin-basket fryer. Wash-up: twin-deck commercial dishwasher. Refrigeration: dedicated under-counter prep fridges. Separate hand-wash basins from prep sinks throughout. Gas Safe-registered commercial engineer commissioning week 7.

Food-Grade Flooring (BoH)

Food-grade safety vinyl flooring in the back-of-house kitchen, cove-skirted to wall to eliminate dirt traps, slip-rated R10 minimum, food-area-compliant chemical resistance. Continuous welded seams. Drainage gully under the cooking line connecting to the fat-trap waste line.

Front-of-House Seating (18 covers)

Bench seat along the south wall (8 covers) with bespoke upholstery in a stain-resistant velvet, three loose tables in front. Window-bar position (4 covers) facing the high street, fixed to brackets clear of the conservation-area window frame. Two communal tables (6 covers) in the central floor area in solid oak with steel legs. Bag hooks under every seat.

Lighting Design (5-Scene)

Front-of-house lighting on a 5-scene controller for daypart shift: bright morning, mid-morning warm, lunch, afternoon mellow, evening warm. Dimmable LED downlights on main grid; two pendant clusters above the central communal tables; low-level shelf-edge lighting in the back bar. Back-of-house at task-lighting brightness for prep clarity.

Conservation-Area Shopfront

Existing timber fascia and pilasters retained, repaired, repainted in heritage-tone dark green agreed in writing with Cheshire East planning. Hand-painted gilded fascia lettering by specialist signwriter; signage consent obtained pre-bid. No alterations to the listed shopfront frame requiring Listed Building Consent.

Pest Control Sealing

All wall-to-floor junctions in the back-of-house and front-of-house service areas sealed with food-grade flexible sealant; service penetrations through walls sleeved and sealed; gaps below all base cabinets minimised; ventilation grilles fitted with insect mesh. Integrated pest-control sealing inspected and signed off by the EHO at the Friday afternoon visit.

EHO & HACCP

Cheshire East Environmental Health Officer pre-opening visit signed off the food safety management system (HACCP), the DW172 grease extraction certification, the hand-wash basin separation from prep sinks, the food-grade flooring cove-skirting, the hot-water provision at every basin, and the integrated pest-control sealing in a single Friday-afternoon visit. Zero remedial actions logged.

Fire & Safety

Smoke and heat detection to BS 5839 Part 1 Category L1 across front-of-house and back-of-house. Fire-rated FD30 separation between the kitchen and the residential flat above (60-minute floor build-up). Canopy fire-suppression system in the kitchen extract canopy with gas-isolation interlock, witness-tested at commissioning.

Performance vs Contracted Targets

Programme
contracted 7 weeks
PC certified on contracted Friday
Final account
contract sum £88,000
£88,000 settled
Variation orders
target 0
0 raised
DW172 grease extract certification
target before EHO visit
certified Wednesday week 7
Cheshire East EHO sign-off
target single-visit pass
single visit, 0 remedial
La Marzocco install
target services-clean
no remedial work logged
Gas Safe commercial commissioning
CCN1+COCN1 certified
commissioned Tuesday week 7
Terrazzo pour-grind-polish-seal
target 5-day workstream
delivered week 5
Conservation shopfront approval
heritage-tone in writing
signed off pre-bid
Soft-launch Saturday opening
contracted soft-launch date
7.30am Saturday opening
RIDDOR-reportable accidents
target 0
0 across 14,000 hrs

The Finished Result

What was delivered

A 110m² specialty coffee shop on the main run through Knutsford delivered against a 7-week fixed-price contract with no variation orders, the DW172 grease extraction route through the existing service riser certified ahead of the EHO visit, the La Marzocco Linea PB and Mahlkönig grinders installed cleanly by the dealer with no service-position remedial, the in-situ poured terrazzo floor delivered as a continuous 5-day workstream in week 5, the bespoke American oak timber-clad serving counter installed by the heritage joiner in week 6, the conservation-area shopfront refreshed in agreed heritage-tone dark green with hand-painted gilded fascia lettering, and the Cheshire East EHO pre-opening visit closed in a single Friday-afternoon visit with zero remedial actions logged.

The first espresso pulled on the soft-launch Saturday morning at 7.30am went to the next-door bookshop owner, who had walked across to say good luck. The first paying customer arrived at 7.34am and ordered a flat white. The Birmingham Colmore Row HQ Fit-Out we delivered earlier in the year had heritage joinery as the spine of a Cat-B office fit-out within a Grade II shell; this Knutsford coffee shop had bespoke American oak joinery as the spine of a hospitality fit-out within a high-street conservation area. Different scale, different use class, different commercial model — same methodology applied to the kind of independent owner-operator project where the photograph in the local paper the Monday after opening matters as much as the contract sum on the day of bid acceptance.

7.30am SatFirst Espresso Pulled
0EHO Remedial Actions
0Variation Orders
1 visitEHO Sign-Off

What the Client Said

I am a former specialty coffee barista with several years behind the bar at a Manchester roastery and Q-grader certification, and Knutsford was my first shop. Every penny of the build budget was mine; every day of slipped programme was a day of rent against a closed shop. I quoted three contractors. Building Group came in second on price by four and a half thousand pounds. I picked them because their quotation was the only one to include the DW172 grease extraction calculation and the route survey through the existing service riser inside the contract sum, the only one to engage the La Marzocco UK dealer at procurement stage so the under-counter services were positioned correctly when the joiner pre-routed them off-site, and the only one to treat the in-situ poured terrazzo as a defined 5-day workstream with the aggregate ordered in week one rather than as a finishing-trade catch-up. The competing quote that was four and a half thousand pounds cheaper had the grease extract as a "subject to landlord" provisional and the terrazzo as a "month-7 finishing item"; either of those would have cost me a slipped soft-launch Saturday and weeks of lost trading. Seven weeks later we had a shop with the EHO signing off in a single Friday afternoon visit with no remedial actions, the La Marzocco pulling its first calibration shot on a Wednesday, and the bookshop owner from next door pulling our first paid coffee at 7.30 on the Saturday morning. The shop is now four months in. We are doing 380 covers a Saturday and our specialty coffee programme runs three single-origin espressos on rotation. We have already booked Building Group for the second site we are scoping in Wilmslow.

Owner-Operator, Independent Specialty Coffee Shop Knutsford, Cheshire · April 2026

More Case Studies

Fitting Out a Coffee Shop, Cafe or Restaurant?

If you're a specialty coffee owner-operator with a high-street unit under lease, an independent restaurateur opening a first or second site, or a small chain expanding into a new town, we'll come out for a free site visit, walk the demised unit with you, and put a fixed-price quotation on your desk — with the grease extraction, the espresso bar service positioning, the kitchen equipment install, the terrazzo or specialist flooring, the bespoke joinery, the conservation-area shopfront permissions and the EHO pre-opening protocol all costed in.