Back to Case Studies Building Group logo Building Group
Case Study · Mansard Loft

Battersea Mansard Loft Conversion

A full mansard loft conversion on a Victorian mid-terrace in a Battersea conservation area, South London — rear roof line raised across the full width of the property, slate-clad mansard cheeks matched to the neighbouring terrace, two new double bedrooms each with a private en-suite, and a sky-lit landing. Approval secured under full Planning Permission, not Permitted Development. Two Party Wall Awards filed before site start. Fourteen-week site programme, fixed price, family in occupation throughout.

Battersea, South London 14 weeks on site £92,000 fixed price +2 bedrooms & en-suites
14 wks Build Duration
£92k Fixed Price
+2 / +2 Bedrooms / En-Suites
2 Party Wall Awards
0 Variation Orders

Project Overview

A professional couple in their early forties with two primary-school-aged children, occupying a four-storey Victorian mid-terrace in one of Battersea's defined conservation areas. They had bought the property three years earlier and had reached the limit of the existing layout: three bedrooms, one family bathroom, no en-suite. The strategic question was about the next fifteen years rather than the next twelve months — the children would be teenagers within six years, both would want their own bathrooms, and the property would benefit from being a five-bedroom rather than three-bedroom Battersea terrace if it ever needed to sell.

Mansard was the right answer for the property type. A hip-to-gable wouldn't have worked — mid-terrace, no hipped roof to convert — and a simple rear dormer wouldn't have delivered the height and floor area needed for two double bedrooms with en-suites. A full mansard, raising the rear roof line across the full width of the property and clad to match the neighbouring terrace pattern, was the design that gave them the floor plan they needed and the visual continuity the conservation area required.

Two competing tenders quoted on the assumption of Permitted Development. They were wrong: this conservation area has Article 4 Direction restrictions removing PD rights for roof extensions, so a mansard requires full Planning Permission, not the lighter PD prior approval route. Our quote at the start identified this and costed the planning application, the heritage statement, the design and access statement, and both Party Wall Agreements (one for each attached neighbour) into the fixed-price preconstruction phase. Pre-construction took seventeen weeks. Site phase ran fourteen weeks. The family stayed in the property throughout.

The Client Brief

The brief was developed over three design meetings. Priorities, in their stated order:

The Challenge

A 14-week mansard in a London conservation area is a regulated, multi-stakeholder build. Six interrelated constraints had to be locked down before the first scaffold pole arrived on site.

Conservation Area & Full Planning

Two competing tenders quoted on the assumption of Permitted Development. They were wrong — the local Article 4 Direction removes PD rights for roof extensions in this conservation area, so a mansard requires full Planning Permission, conservation officer engagement, and a heritage statement justifying material choices. We led the process: pre-application meeting with the conservation officer in week 2, planning drawings and heritage statement submitted in week 4, determination at week 12 (eight weeks of statutory determination), approval issued with one minor condition agreed.

Two Party Wall Awards

Mid-terrace properties have two attached neighbours; mansard work requires Party Wall Notices on both. We served both notices in week 2 of pre-construction. One neighbour consented in writing within two weeks. The other appointed an agreed surveyor; surveyor process ran from week 6 to week 14 with two site visits, a draft schedule of condition, and the Award filed in week 15. Both Awards in place before site start, no objections, no party wall surveyor fees passed back to the clients (costed inside our fixed price).

Mansard Structural Design

A mansard converts roughly 40m² of floor area onto the third storey. Structural design needs three primary steels: a transverse ridge beam at the new ridge, a longitudinal eaves beam at the front parapet level (transferring loads to the existing front and rear walls), and a transfer beam across the new floor where the existing third-storey ceiling joists were undersized for habitable load. All three sections calculated to BS EN 1993, signed off by our structural engineer and reviewed by Building Control at plans stage.

Slate Cladding to Match the Terrace

The conservation officer's first request was a heritage match for the slate. The neighbouring terrace uses Welsh Penrhyn-style natural slate — specific colour, specific weathering pattern, specific dimensional tolerance. We sourced from a salvage yard supplying reclaimed Welsh slate from a similar-vintage roofing demolition, sample-confirmed against three of the closest neighbouring properties, and pre-agreed with the conservation officer before the planning application went in. Approved without amendment.

Fire & Sprinklers (Part B + BS 9251)

Loft conversions creating a fourth habitable storey require additional fire protection beyond the standard third-storey rules: a domestic sprinkler system to BS 9251 across the new floor in addition to the protected escape route, FD30 fire doors throughout the escape, and mains-wired interlinked smoke alarms on every floor. Sprinkler system designed by a BAFE-registered specialist, pressure-tested at first fix, commissioned with hydraulic flow test at handover.

London Site Logistics

No off-street parking, narrow front access, scaffolding licence required from the local highways authority, controlled-hours vehicle deliveries (no large vehicles before 7am or after 6pm Mon-Fri, none on weekends). We applied for the scaffolding licence in week 1 of pre-construction, scheduled all major material deliveries in 90-minute windows during permitted hours, and pre-booked the steel-beam crane lift for a Saturday morning under a separate one-off Saturday permit. Zero deliveries blocked, zero parking complaints from neighbours.

Our Approach

London conservation-area mansards are, in practice, two projects: a planning project and a building project. Our approach was structured around four disciplines covering both halves.

Pre-construction owned end-to-end, costed into the fixed price. Planning application, heritage statement, conservation officer engagement, two Party Wall Notices and Agreements, Building Control plans submission, and the scaffolding licence application were all led by us. Pre-construction ran seventeen weeks. The clients had nothing to do except read our weekly updates and sign documents when asked. No separate planning consultant, no separate party wall surveyor billed to them, no scaffolding licence fees on top of the contract sum.

Conservation officer engaged before submission, not after. The two competing tenders were planning to "submit and see what comes back." We held a pre-application meeting with the conservation officer in week 2 of pre-construction, walked them through the proposed slate match, the mansard set-back from the front parapet, the rear elevation detailing, and the preserved street-view. Their conditional approval at meeting stage shaped the planning submission. Determination at week 12 produced one minor amendment on rooflight position. No fundamental redesign, no resubmission.

Structural design before quote, not after deposit. Three primary steels modelled, calculated and priced at quote stage. The clients saw the structural calculations and the steel schedule before they signed the contract. No "we'll work that out when we open the roof up" — everything modelled and drawn before the first slate came off.

Roof watertight by Friday of week 6 as a calendar commitment. Open-roof phase runs longer on a mansard than on a hip-to-gable because the entire rear roof structure is being rebuilt, not just the hip end. We costed in a full weatherproof scaffold tent as a fallback at quote stage, with a hard hold-point of "roof watertight by Friday of week 6." The forecast in week 5 showed a wet weekend coming; the tent was deployed on the Saturday and stood until the following Wednesday. Total forecast risk premium covered by the costed-in fallback. No water ingress at any point.

The Build Process

Seventy working days on site, preceded by seventeen weeks of pre-construction (planning, conservation, both party wall agreements, building control plans approval, scaffolding licence). Site programme sequenced against a Friday-of-week-6 watertight hold-point and a Friday-of-week-14 handover.

00
Pre-Site (17 weeks)

Planning, Conservation, Party Wall & Building Regs

Planning drawings, heritage statement, design and access statement prepared. Pre-application meeting with conservation officer (week 2). Two Party Wall Notices served (week 2). Planning application submitted (week 4). Party wall surveyor process for non-consenting neighbour (weeks 6-14). Planning approval issued (week 12). Both Party Wall Awards filed (week 15). Building Control plans submitted (week 15) and approved (week 16). Scaffolding licence granted (week 17). Site start the following Monday.

01
Week 1

Scaffolding, Strip-Out & Roof Demolition

Full perimeter scaffolding erected to the new ridge height with edge protection and a controlled access ladder. Existing rear roof tiles, battens and rafters carefully demolished. Existing third-storey ceiling joists protected to maintain second-floor ceiling integrity. Sealed plastic dust separation at the second-floor stairwell head. Building Control foundation/structural inspection booked for week 3.

02
Week 2

Mansard Structural Frame & Steels

Three primary steels delivered and craned into position over a Saturday morning under a one-off Saturday permit. Transverse ridge beam set first, longitudinal eaves beam set second, transfer beam across the new floor third. All bolted to padstones and to the existing structural masonry. Mansard timber stud frame erected against the steel skeleton at a 70-degree pitch on the rear and side cheeks.

03
Week 3

New Floor Joists & Internal Stud Walls

New floor joists installed at 400mm centres, hangered into the steel transfer beam and bolted to the existing structural walls. Floor decking laid Friday afternoon. Internal stud walls framed for the two new bedrooms and the central landing. Building Control foundation/structural inspection signed off Tuesday afternoon.

04
Week 4

Roof Decking, Felt & Lead Flashing

Mansard cheek decking installed across rear and side faces in 18mm WBP plywood. Roofing felt lapped and battened. Lead flashing dressed at all junctions: ridge, valleys, parapet abutments, dormer cheeks. First-stage weatherproof envelope complete by Friday. Three Velux roof windows ordered and scheduled for week 5 install.

05
Week 5

Velux, Slate Sourcing & Weather Tent

Three Velux roof windows installed (one to each new bedroom, one to the central sky-lit landing). Forecast review on Wednesday flagged a wet weekend coming; weatherproof scaffold tent deployed on Saturday morning, providing full envelope protection through Sunday and Monday. Reclaimed Welsh slate delivered to site Monday afternoon, sample-confirmed against three neighbouring properties before installation. Slate cutting setup arranged on the lower scaffold deck.

06
Week 6

Slate Cladding & Roof Watertight (HOLD-POINT)

Reclaimed Welsh slate cladding installed across the rear and side mansard cheeks. Slate hung in a coursing pattern matched to the neighbouring terrace, sample-checked against the conservation officer's approved photograph at every course. Lead flashing dressed at all junctions. Friday afternoon: full mansard roof envelope watertight, photographed and signed off as the project's hard hold-point. Internal works can now proceed weather-independent. Conservation officer site visit Tuesday following: slate match approved, no remedial work requested.

07
Week 7

First Fix Services & Sprinkler System

Electrical first fix throughout the new floor and the upgraded escape route: bedroom and en-suite circuits, mains-wired interlinked smoke alarms on every floor of the house. Plumbing first fix to both en-suites: hot/cold supplies, soil routing through new floor void with 1:40 fall to existing stack on each side. BS 9251 domestic sprinkler system installed across the new floor by BAFE-registered specialist, pressure-tested. Pre-plaster Building Control inspection signed off Friday.

08
Week 8

Insulation & Plasterboard

Warm-roof construction insulation: 150mm PIR between rafters and within mansard cheeks with a 50mm air gap above and 25mm PIR underdraw. Calculated U-value 0.15 W/m²K, beating the 0.18 W/m²K Part L target. Full vapour control layer sealed at every penetration. Plasterboard fitted throughout, including 12.5mm fire-rated board to the protected escape stairwell and around the steel ridge beam encasement. Two coats of plaster, finishing skim.

09
Week 9

Stairs Install & Both En-Suites Tanked

New softwood-and-MDF staircase fabricated off-site delivered Monday and installed Tuesday-Wednesday: landing onto the existing second-floor landing, no impact on existing bedroom footprint. Schluter Kerdi tanking applied across both en-suite floors and walk-in shower walls, sealed at every penetration. 24-hour static flood test on each en-suite Wednesday-Friday: both passed and signed off independently. Drainage Building Control inspection signed off Friday.

10
Week 10

UFH, Screed & En-Suite Tile Install

Wet UFH manifold positioned in the new utility cupboard, pipework laid in both en-suites at 200mm centres, screed poured Monday over the cured tanking layer. Large-format porcelain tile installed across both en-suite walls and floors Wednesday-Friday. Continuous pattern-matched at internal corners.

11
Week 11

Decoration, FD30 Doors & Sprinkler Commission

Decoration started in both new bedrooms and on the landing: two coats of mist coat plus first topcoat. FD30 fire-rated doors installed at all stair-adjacent rooms along the protected escape route, intumescent strips and smoke seals fitted. Sprinkler system commissioned with hydraulic flow test, certificate filed. Conservation officer follow-up site visit cleared the slate match for the planning condition file.

12
Week 12

En-Suite Sanitaryware & Brassware

En-suite sanitaryware installed in both rooms: walk-in showers (frameless 10mm tempered glass screens), single basins on fitted vanities, wall-hung WCs with concealed cisterns, heated towel rails. Brassware connected and tested. Second-fix electrics throughout the new floor and along the escape route: light fittings, sockets, smoke alarms commissioned and tested.

13
Week 13

Wardrobes, Stair Balustrade & Final Decoration

Built-in wardrobes installed in both new bedrooms: full-height carcasses, sliding-door fronts, internal hanging and drawer fittings. Stair balustrade installed to all flights from the new floor down to the ground floor. Final decoration: second topcoats throughout, skirtings re-fitted. Pre-completion Building Control inspection booked for week 14.

14
Week 14

Snag, Building Control Sign-Off & Handover

Carpets fitted in both new bedrooms and on the landing. Snagging walkthrough Monday; eleven items identified, eight cleared by Wednesday afternoon. Final Building Control completion inspection Thursday morning; certificate issued Friday by post (received Tuesday following). Handover Friday at 4pm. Family stayed in the property the entire fourteen weeks.

Project Specifications

The technical detail behind a London conservation-area mansard delivered to full planning, two party walls, and seven Building Control inspections.

Structural Steels

Three primary steels calculated to BS EN 1993. Transverse ridge beam: 254 × 146 UB at 6.2m span. Longitudinal eaves beam: 203 × 102 UB at 5.4m span. Transfer beam at new floor: 305 × 165 UB at 5.4m span. All bolted to padstones bedded over existing structural masonry. Steels encased in 30-minute fire-resistant boarding.

Mansard Structure

Timber stud frame at 70-degree pitch on rear and side cheeks against the steel skeleton. 18mm WBP plywood decking. Lead flashing dressed at all parapet abutments and dormer junctions. Front elevation set back from the existing parapet line to remain visually unaffected from street level (planning condition).

Slate Cladding

Reclaimed Welsh slate sourced from a salvage yard supplying similar-vintage roofing demolitions. Sample-confirmed against three neighbouring properties before installation. Hung in a coursing pattern matched to the neighbouring terrace. Conservation officer-approved at planning stage and sign-off site visit.

Insulation & Thermal

Warm-roof construction. 150mm PIR between rafters with 50mm air gap above, plus 25mm PIR underdraw. Mansard cheek insulation 150mm PIR within stud cavity. Calculated U-value 0.15 W/m²K, beating Part L 0.18 target. Full vapour control layer at every penetration.

Fire Strategy (Part B + BS 9251)

Protected escape route from new floor to ground floor: 30-minute fire-resistant construction along stairwell. FD30 fire doors at all stair-adjacent rooms with intumescent strips and smoke seals. Mains-wired interlinked smoke alarms on every floor. Domestic sprinkler system to BS 9251 across the new floor, pressure-tested and commissioned.

Stairs (Part K)

New softwood-and-MDF staircase fabricated off-site, landing onto the existing second-floor landing rather than into a bedroom. Pitch 41 degrees, clear width 800mm, headroom 1.94m at the worst point. Hardwood handrail at 900mm, toughened glass balustrade panels.

En-Suites (x2)

Each en-suite: walk-in shower with frameless 10mm tempered glass screen, brass-finish thermostatic valve, overhead rainfall plus hand-held shower. Single basin on fitted vanity with marble-effect porcelain worktop. Wall-hung WC with concealed cistern. Heated towel rail. Wet UFH below large-format porcelain. Schluter Kerdi tanking, 24-hour flood test passed on each.

Velux & Sky-Lit Landing

Three Velux GGL Centre-Pivot UFC roof windows: one to each new bedroom, one to the central landing creating the sky-lit corridor between the two rooms. Double-glazed, U-value 1.0 W/m²K, white-painted timber frames internally. Manual operation via reach-pole on the landing window.

Performance vs Contracted Targets

Pre-construction phase
expected 14–20 weeks
17 weeks, all consents
Site programme
contracted 14 weeks
delivered day 70
Final account
contract sum £92,000
£92,000 settled
Variation orders
target 0
0 raised
Roof watertight hold-point
target end of week 6
Friday week 6, signed
Conservation officer sign-off
target post-cladding
approved without amendment
Roof thermal U-value
target ≤ 0.18 W/m²K
0.15 W/m²K achieved
Snag list at handover
target ≤ 16 items
11 items, all cleared in 8 days

The Finished Result

What was delivered

A 3-bed Victorian mid-terrace in a Battersea conservation area converted into a 5-bed terrace with two new en-suites, delivered against a 14-week site programme on a fixed-price contract preceded by 17 weeks of pre-construction. Three primary steels carry the new roof structure, the mansard cheeks are clad in reclaimed Welsh slate sample-matched to the neighbouring terrace, and the conservation officer's sign-off site visit cleared the planning condition file at week 11. From the street, the front elevation reads exactly as it did before; from the rear and from the gardens behind, the new roof line reads as a continuous extension of the row.

The two new bedrooms each have full standing headroom across the usable footprint, both have private en-suites, and the central sky-lit landing under the Velux gives the new floor a natural-light core. The clients' framing of the project, after handover: "We bought this house for the next twenty years. We've added the bedrooms we know we'll need." The eldest child has chosen the bedroom looking south over the garden; the second has chosen the slightly larger one with the better en-suite. The original first-floor bathroom is now used by parents only. The home office on the second floor stays where it was.

14 wks Delivered to Programme
0 Variation Orders
2 Party Wall Awards Filed
+2 / +2 Bedrooms & En-Suites

What the Client Said

We had three contractors quote. Two of them assumed Permitted Development and quoted on that basis. Building Group identified at the first site visit that our conservation area has Article 4 restrictions removing PD rights for roof extensions, that we'd need full Planning Permission, and quoted accordingly — with the planning application, the heritage statement, both Party Wall Agreements, building control and the scaffolding licence all bundled into a single fixed price. That single conversation was the moment we chose them. Pre-construction took seventeen weeks; we had nothing to do except read the weekly updates. Site phase ran fourteen weeks; the family stayed in the house throughout, the school runs were never disrupted, and the slate match on the rear cheeks is genuinely indistinguishable from our neighbours' roof from any angle. The eldest has the south-facing room. The second has the bigger en-suite. We've got the bedrooms we'll need when both of them are teenagers, in five or six years' time. We'd recommend them without hesitation.

Homeowners Battersea, South London · April 2026

More Case Studies

Planning a Mansard or Conservation-Area Loft?

If you own a Victorian or Edwardian terrace in a London conservation area and you're thinking about a mansard, a rear dormer or a hip-to-gable, we'll come out for a free design consultation, walk the property with you, identify whether full planning or PD is the right route, and put a fixed-price design-and-build proposal — with the planning application, party wall agreements, conservation engagement and building control all costed in — on your kitchen table within fifteen working days.

Get Your Free Quote